Acceptance testing milestone achieved
Plant Acceptance Testing was successfully completed on the first attempt, for the Stage 2 CHPP at our Byerwen site.
This milestone was achieved five days prior to the contractual practical completion date and only ten days after the commencement of load commissioning.
Thanks to a great team effort and excellent collaboration with the client and subcontractors, these significant construction and commissioning works were completed without serious injury or incident.